Forum Discussion
Altera_Forum
Honored Contributor
8 years agoMAX10 - Can we power up IO banks separately at different times for power sequencing?
We have a module connected to the 10M02 CPLD that requires a specific power sequence, many signals from that module are connected to the MAX10. Upon start up we want to first send a start signal from...
Altera_Forum
Honored Contributor
8 years agoHi,
Design power sequencing and voltage regulators for the best device reliability—although power sequencing is not required for correct operation, consider thepower-up timing of each rail to prevent problems with long-term device reliability if you are designing a multi-rail powered system. https://www.altera.com/en_us/pdfs/literature/hb/max-10/m10_guidelines.pdf Best Regards, Anand Raj Shankar (This message was posted on behalf of Intel Corporation)