Altera Cyclone V FPGA 5CGTFD5C5U1917N

The Altera Cyclone V FPGA 5CGTFD5C5U1917N FPGA has a two year lead time as of 9/21/2023. Is there hope that this lead time will shrink? Are there surrogates for this package?

3 Replies

  • NazrulNaim_Intel's avatar
    NazrulNaim_Intel
    Icon for Regular Contributor rankRegular Contributor

    Hi,

    Thank you for reaching out. Allow me some time to look into your issue. I shall come back to you with findings.

    Thank you for your patience.

    Best Regards,

    Nazrul Naim


  • NazrulNaim_Intel's avatar
    NazrulNaim_Intel
    Icon for Regular Contributor rankRegular Contributor

    Hello,


    Sorry for the delay. After discussing with the internal teams. The latest Lead Time for this Device will be 20 weeks.


    Hope that answers your question.


    Best regards,

    Nazrul Naim


  • NazrulNaim_Intel's avatar
    NazrulNaim_Intel
    Icon for Regular Contributor rankRegular Contributor

    Hi,

    As we do not receive any response from you on the previous question/reply/answer that we have provided, for now I will set this case to Close-Pending.

    Regards,

    Nazrul Naim